The district received an Observation Report by Ensign Engineering on the condition of Timpview High. Below is the report.
The intent of the site visit was to review signs of new/additional settlement within the school.
Items observed were primarily located in the media center, south academic wing, and west academic wing. The observations were strictly visual. No testing or scanning was performed.
The fact that the building continues to show signs of settlement and distress reinforces the need of remediation and stabilization at this site if the PCSD decides to not build a new facility. It is our opinion that the building will continue to settle, and will further present additional signs of distress over time.
Sincerely, Scott B. Roche, PE, SE Principal from Ensign Engineering
As part of the Safety and Security Campaign, we want to inform all families of a significant asset...
In Katherine Puzey's second grade classroom at Sunset View, students are reading texts, using...
Rock Canyon Media Center Monday, February 6, 6:30-7:30 pm Timpanogos Media Center...