Skip To Content Skip to Translation Menu
Search Icon

At the recent School Board meeting, Westland Construction provided a detailed update on ongoing construction projects within the district, primarily focusing on Timpview High School. The presentation showcased significant milestones and upcoming plans designed to improve the facilities while efficiently managing costs and timelines.

Watch the PCSD Board Study Session meeting for a more comprehensive review of the construction projects in our district.

The following is an overview of the updates provided.

Timpview High

Softball Field and South Parking Lot  

Westland Construction has made impressive strides at Timpview High, completing the detention pond designed to handle water runoff. Concrete pours for the batting cages and bullpens followed the completion of the detention pond. Preparations are underway for the outfield fence line, and sod installation is expected by the end of the month, ensuring the field is ready for use next spring. Meanwhile, work on the south parking lot is nearly complete, with teacher access anticipated by next Friday. Additional parking will be ready in the fall, though it will remain a construction zone until further work concludes.

The right image shows the finished detention pond near the Timpview softball field, with gravel installed to collect runoff. The left image depicts the south parking lot, where construction crews prepare for concrete pours.

  Dance and Fitness Building, Wrestling Room, and North Gym

Progress continues in multiple areas across the campus:

  • The wrestling room’s masonry is complete, and scaffolding will be removed this week. Steelworkers are now installing beams in the wrestling room.
  • The north gym now has a roof, with skylights to be installed soon. Painters should visit the north gym soon, too.
  • Electrical work is ongoing in the fitness building.

Commons Area and Mechanical Room

The commons area remains closed to students due to Fire Marshal regulations requiring adequate air movement, which will only be possible once Westland Construction completes construction on the mechanical room.

Westland Construction is targeting February 2024 to reopen the commons, with mechanical work progressing and flooring issues resolved.

The upper right image highlights the incomplete dance and fitness building, with joists set in place, awaiting deck installation. The left image shows the wrestling room, with surrounding scaffolding removed and beams being installed.

Great Western Landscape and Future Admin Area

Plans for the future admin and counseling area are well underway. As part of the next phase of construction, storm drain’s are being rerouted to decrease phase 2 construction costs, and additional work on cobble installation and minor foliage removal on the sidewalk along Timpview Drive and Timpview’s Southwestern corner is expected to proceed, per city code.

Timpview Slide 4:
On the right side, a cost overview is provided, listing storm drain prices and cobble installation costs. The left image shows a blueprint of the school's interior, with future areas for the admin, counseling, and performing arts highlighted.
Verbatim Text on Slide:
Right Side Text:
"KSC - Storm Drain Price: $201,080"
"Great Western Landscape - Cobble: $14,923"
"If we had proceeded per plan, cost would be $750K in utility rework. Savings: $549K."
Left Image: Blueprint of future admin/counseling area and Performing Arts/CTE addition:
Red Textbox (Top left): "Future admin and counseling area."
Red Textbox (Below): "Rough outline of future auditorium / Performing Arts / CTE addition shown as in lavender."

Wrestling Room and Thunderdome Roof

Upgrades to the Thunderdome entryway and vestibule include:

  • Skylight installations.
  • Heavier joists to handle snow loads.
  • A mechanical rework to vent air through the roof rather than the walls.

Though requiring upfront costs, these changes will prevent more expensive retrofitting later. The use of credits and on-site materials has helped keep costs down.

Right Image: "Skylight Openings: Shown on the roof. Painters scheduled for next month. Electrical work ongoing through October."
Other Notes: "Masonry completed. Mechanical rough completed. Acoustic insulation sprayed."

Vestibule and Cafeteria Remodel

Westland Construction is in the final stages of refining plans for the vestibule, which will now feature skylights to brighten a dark space. A cafeteria remodel and additional new plans are also underway, with efforts focused on minimizing rebuilding and maximizing cost efficiency. Roofing credits have already saved $184,000. All sections in red will be removed in Phase 2, with the gray sections remaining. 

The left graphic showcases the new vestibule plans, with sections for pillars, canopy, and roofing highlighted in red. The right side lists savings from reduced material costs and repurposed construction elements.
Verbatim Text on Slide:
Right Side Text:
"B&D Glass - Windows = $-90,214"
"Buxton - Masonry Infills = $-45,000"
"Buying Joists = $-35,000"
"Clegg - Canopy = $13,944"
"Total Credit = ($184,158)"
Image Captions:
Top Image: "South Elevation"
Bottom Image: "West Elevation"

Change Orders and Final Costs

Westland is working hard to balance change orders with credits, on-site materials, and employed workers. Notable change orders include adjustments to the vestibule, the South Gym, the Thunderdome entry roof, and landscape modifications. Below is a list of the change orders and associated costs, as well as notation regarding which amounts are covered, full or partially, through credits retained via strategic construction during this phase:

  • Vestibule costs are $9,046, but we’re working to cover this with roofing credits.
  • South gym costs are $4,529. We’ve just started working on the structure and rebuild for this area.
  • No changes to the South Access landscape due to previous adjustments with materials and building.
  • Thunder Dome entry roof costs $31,162, but we’re planning to use roofing credits to offset this amount.
  • The City required a 6-foot buffer between the road and sidewalk, leading to additional costs of $25,165 for cobble, a retaining wall, and landscaping fixes.
  • Future landscape changes will cost $14,923.
  • A temporary egress was required by the Fire Marshal, costing $36,750.

All Phase 2 changes total $415,675, factoring in both costs and credits– this amount does not account for specific credit usage, which will cover a significant portion of the costs. We’re getting close to wrapping up this phase!

Verbatim Text on Slide:
"PR 81 - Vestibule 107 - $9,046"
"PR 92 - South Gym - $4,529"
"PR 94 - South Access Landscape - $0"
"PR 89 - Thunderdome Entry Roof - $31,162"
"PR 95 - Phase 2 Changes - $415,675"
"RFI 491 - Parking lot to sidewalk grade - $25,165"
"PR 97 - Landscape changes for the future - $14,923"
"Fire Marshal required temp egress: $36,750" 

Shoreline Middle School and Wasatch Elementary Updates

Shoreline Middle School is nearing completion, with 90% of previous punch-list items addressed. A few teacher requests and minor furniture adjustments are still in progress, but the project is wrapping up nicely overall.

At Wasatch Elementary, construction has advanced significantly following receiving a crucial electrical panel. The project is in good shape, with the final ship date for the remaining items set for October 1st. Improvements include the removal of previously exposed beams, which have now been dry-walled and painted for a more polished finish. The change order for railings and guards is complete and will be finished on schedule.

For future updates on construction projects, follow us on Instagram and Facebook at @provocityschooldistrict, or subscribe to the Construction Newsletter using the link below.

Spencer Tuinei
  • Communication Specialist
  • Spencer Tuinei
0 Shares
en_USEnglish