THS: Updates on softball fields, parking lots, dance and fitness rooms, and a change in drainage, roofing, and landscaping to save money in a possible future phase.
Shoreline: 90% done with punch list; furniture ordered per some teacher requests
Wasatch: We are still waiting for some equipment, but work has continued to prepare for what is still coming. Some items have been changed since the tour: i-beams are enclosed instead of exposed, railings have been changed, etc.
1005 School Boundary and Closure Policy, bringing in line with current legislation
1405 School Closures and Boundary, a model policy to bring in line with legislation, some suggestions made to references and language. This is a first reading. This will be researched and make sure suggested changes will work with legislation.
1509 and 1529 Updated Superintendent and Business Administrator Dismissal Policies, updating to make current with state statutes.