Skip To Content Skip to Translation Menu
Search Icon

During the September 10, 2024 School Board Study Session, the board received detailed reports on the construction projects at Timpview High and Wasatch Elementary.

Watch the PCSD Board Study Session meeting for a more comprehensive review of the construction projects in our district.

The following is an overview of the updates provided.

Timpview High School

The dance cardio walls are complete, and the north gym walls and roof are complete. The next step towards completing the northern gymnasium involves finishing construction on the mechanical room, the wrestling room, and the adjoining classrooms in that order. The gymnasium flooring, however, requires time to settle in a conditioned environment before they can install said flooring and complete the northern gym. At said point, construction can continue in the mechanical room and classrooms. Construction teams will also move wall joists using a crane in upcoming weeks. Once they have completed the flooring and crane usage, they can commence building the mechanical room and installing the mechanical system.

Commons Area and Mechanical Room  

During the most recent ‘Sup with the Sup’ podcast, Student Board Representative Monika Tua’one asked about the timeline for the Commons Area completion and commencement. Currently, the Commons is being used to store mechanical equipment. Our construction team asked if they could move the stored equipment to some potential storage spaces, but the Fire Marshal has prohibited the use of the new Commons area on grounds of safety and code issues. Once construction concludes on the Mechanical Room– anticipated by February 19– construction teams will move the equipment to the new Mechanical Room, allowing for swift work on the Commons Area to commence and a swifter commencement of the Commons.

Southwest Parking and Landscaping

Landscaping for the southwest parking structure will begin shortly to ensure the installation of foliage and asphalt before winter. Aerial views show progress on grading, asphalt, and utilities in the parking areas.

Athletic Facilities

Work on the softball field dugouts and asphalt is progressing as scheduled. The landscaping for the South Access road, including tree and sod installations, is complete. The temporary concession stand window will remain in place until the permanent window arrives.

Cafeteria

The design phase for the new cafeteria is nearly complete, and construction on the cafeteria is expected to begin soon thereafter.

A low-angled shot of the northern gym interior roofing beams. A low-angled shot of the northern gym interior roofing beams. A sliding window attached to the concession stand. A wooden slat is anchored to the masonry, holding the window in place. A drone shot of the South Exterior walkway near the Football field. There is sod planted near the new sidewalk, as well as an island between the sidewalk and the adjoining neighborhood houses. The island contains red stone and planted trees. A long, high-angled shot of the sotball dug-out rebar, with a white truck in the background. Behind the rebar sits a bundle of plywood. Bird's eye view of the Softball dug-out. In the top right-hand corner of the lot, one can see the concrete dug-out, buried in the dirt, as well as rebar sticking from the ground, making the square for where the pitching mound and fence will be installed. Bird's eye view drone shot of the bulldozed lot. A long drone shot of the southwestern corner of Timpview High School. On the right lays the bulldozed lot, and on the left, concrete sidewalks and newly planted trees. In the far left, across the street, stands Edgemont Elementary. A long drone shot of the north gym reveals that the roof is complete and that the walls of the dance area are enclosed. A crane sits on the bulldozed space in the bottom quadrant of the picture. Timpview High School's southwest bulldozed parking lot is shown from a long angle, with a mountain range in the background. A captioned word, "Timpview," hovers above the school.

Wasatch Elementary School

Substantial progress has been made at Wasatch Elementary to ensure most of the installation and exterior construction concludes before winter. All roofing is now complete. Landscaping continues, with trees recently planted around the school grounds.

Sound absorption panels and ceiling tiles were recently installed near the school’s main entry. Following fire inspection and Fire Marshal approval, construction teams will install ceiling tiles in the second-floor hallway and kindergarten.

Our interior teams have installed kitchen tiling and will soon install kitchen appliances. Mechanical equipment and piping are already in place, and the electrical gear arrived on time thanks to an expedited shipping process.

With all the necessary materials, the project is on track to complete on January 15, 2025.

Wasatch Elementary School's red brick facade and exterior with the mountain range in the background. A captioned word, "Wasatch," hovers above the school. A far exterior drone shot of the Wasatch Elementary school. A grass field and asphalt drop-off exterior lot can be seen. A bird's eye view of the school roofing. The roofing is complete. A long shot of the asphalt drop-off loop. A construction worker stands near several potted trees. A medium shot of the Wasatch entrance hallway angled upwards so you can see the roof tilling. Twenty wooden cabinets line the corner of a classroom wall. A medium shot of the Wasatch Elementary hallway angled upwards so you can see the roof tilling. A landscape shot of the Wasatch Elementary Kitchen; the image is angled downwards to show brown, hand-span-sized tiles. A medium shot of the road above the Wasatch Elementary school. Jersey-styled concrete barricades line the student walkway, protecting them from traffic.

For future updates on construction projects, follow us on Instagram and Facebook at @provocityschooldistrict, or subscribe to the Construction Newsletter using the link below.

Spencer Tuinei
  • Communication Specialist
  • Spencer Tuinei
0 Shares

On Monday, November 18, Lakeview Elementary held its annual art show Art teacher Elicia Gray...

en_USEnglish