Shoreline Middle Project

Project Scope

This project is a new middle school to replace Dixon.

Project Manager Trent Huntsman
Architect Curtis Miner
General Contractor Westland Construction
New/Added Gross Square Feet New
Renovations Gross Square Feet N/A
Project $ Per Square Foot TBD
Construction $ Per Square Foot TBD
General Obligation Bonds & Reserves Interest Rate 2.6%

Budget

Budget Item Current/Approved Anticipated
Construction $61,668,688 $2,723,466
Soft Cost $3,000,000 $0
Predesign, Planning & Design $2,529,990 $2,182,759
Furnishing, Equipment & Tech $1,243,766 $0
Contingency $1,650,000 $0
Testing & Inspection TBD $22,880
Other Costs $1,075,000 $60,000
Total Project Costs $71,167,444 $4,989,104

Schedule

The project is 4.24% complete as of 10/21/2022.

Construction Footage

Drone footage from October 2022

Drone footage from September 2022.